M.P. AUDYOGIK KENDRA VIKAS NIGAM (INDORE) LTD., INDORE.
DOCUMENT FOR PERCENTAGE RATE TENDER
FOR
Supply, Installation, Testing and Commissioning of 33/11 KV External Electrification

work for New Industrial Area at Hatod Sardarpur Distt. Dhar


Estimated Cost Rs. 8,34,41,000/- Earnest Money Rs. 8,34,410/-

Managing Director

Madhya Pradesh Audyogik Kendra Vikas Nigam (I) Ltd., Indore
September - 2014

Tender Document


Office of the : MPAKVN(I)Ltd., Indore

NIT number and Date : 10907 dt. 02.09.2014

Agreement number and Date : _______________________________________________

Name of work : Supply, Installation, Testing and Commissioning of 33/11 KV External Electrification work for New Industrial Area at Hatod Sardarpur Distt. Dhar

Name of the Contractor : _______________________________________________

Probable Amount of contractor

(Rs. In figure) : Rs. 8,34,41,000/-

(Rs. In words) : Rs. Eight crore thirty four lakh forty One

thousand only.

Contract Amount

(Rs. In figure) :_______________________________________________

(Rs. In words) :_______________________________________________

Stipulated period of completion : 18 months including rainy season

Appendix 2.10
Tender Document
Table of Contents


Section No

Particulars

Page No.

Section 1

NIT

3-5

Section 2

Instructions to Bidder (ITB)

6-14

Bid Data Sheet

15-17

Annexure A to M

18-223

Section 3

Table of Clauses

224-225

Part-I General Condition of Contract (GCC)

226-241

Contract Data

242-246

Annexure N to W

247-276

Part-II Special Condition of Contract (GCC)

277-278


Section 4

Bill of Quantities (BOQ)

279-318

Section 5

Agreement Form

319

SECTION 1

Notice Inviting E-tender
M.P. AUDYOGIK KENDRA VIKAS NIGAM(INDORE) LTD., INDORE
N.I.T. No. 10907 dated 02.09.2014

Online percentage rate bids for the following works are invited from registered contractor and firms of repute fulfilling registration criteria:


Sr

Work

District’s

Probable Amount (Rs. In Lakh)

Completion period

(months)

1

Supply, Installation, Testing and Commissioning of 33/11 KV External Electrification work for New Industrial Area at Hatod Sardarpur Distt. Dhar

DHAR (MP)

834.41

18 Months (including rainy season)




  1. Interested bidders can view the NIT on website http://www.mpeproc.gov.in




  1. The Bid Document can be purchased only online from 10:30 on 03/09/2014 to 17:30 on 01/10/2014.



  1. Amendments to NIT, if any, would be published on website only, and not in newspaper.

Managing Director

MPAKVN(I) Ltd., Indore

Notice Inviting Tender

M.P. AUDYOGIK KENDRA VIKAS NIGAM (INDORE) LTD., INDORE

N.I.T. No. 10907 dated 02.09.2014
Online percentage rate bids for the following works are invited from registered contractor and firms of repute fulfilling registration criteria:

Sr. No


Name of work

District (S)

Probable Amount of contract

(Rs. In lakh)

Earnest money deposit (EMD)

(in Rs.)

Cost of Bid document (in Rs.)

Category of contractor

Period of completion

(in months)


1


Supply, Installation, Testing and Commissioning of 33/11 KV External Electrification work for New Industrial Area at Hatod Sardarpur Distt. Dhar

DHAR (MP)

834.41 lacs

8,34,410/-

20,000

The Contractors (registered in appropriate class in PHED, PWD, WRD, CPWD, Railways, MES or any other state government/ central government undertaking/ organizations) who have got adequate financial resources, state of the art technology, suitable construction equipments, technical manpower and sufficient past experience satisfying the technical and financial criteria are eligible to apply. For Electrical work


18 Months (including rainy season)
  1   2   3   4   5   6   7   8   9   ...   44

Share in:

Related:

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconSupply installation testing & commissioning of air conditioners at peroorkada factory

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconSupply, Installation, Testing and Commissioning of 2 X 700 tr central...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconSub : Tender enquiry for Supply, Installation and Commissioning of...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconHave Varied Experience of in Project/ Routine Maintenance, Installation,...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification icon1. Organizations use this transaction set to order items of supply,...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconSenior level managerial assignments a Installation and Commissioning...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconGuidelines for installation of remote dspts. A : Supply of materials & safety of storage

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconManual agc, separate Bass and Treble controls, provisions for External...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconTesting your Installation

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconNo of days after Commissioning

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconInstallation On the installation of the hssb drivers, Ncboot32. exe...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconInstallation On the installation of the hssb drivers, Ncboot32. exe...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconProfile Instrument Technician (Pre-Commissioning)

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconSchedule testing with Owner’s Representative a minimum of three (3) days in advance of testing

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconTest rail welds through the use of a certified testing agency using...

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconExternal case user's manual

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconExternal case user's manual

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconExternal case user's manual

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconAll Platforms (internal & external users)

For supply, Installation, Testing and Commissioning of 33/11 kv external Electrification iconExternal enclosure user's manual